City of Broken Arrow Streets Rehabilitation Project @ SCF
Posted on Jul 3rd, 2026

The City of Broken Arrow held a public meeting on June 25th at Liberty Elementary to share details of the street rehabilitation project for Steeplechase Farms.  The following were key highlights noted from that meeting.
 
Schedule/Timing - initial project estimate ~120 days
o   Starts Aug 3rd and runs through the end of November, weather dependent 
o   Work will be done Monday-Friday from 7:00am to 5:30pm
o   On average, each section will take no more than 5 days to complete - start to finish
 
Scope
o   Cherokee Pride Construction was awarded the contract for the project.
o   Various pavement sections will be removed and replaced with multiple levels of underlayment, aggregate rock, rebar support and cement applied - Click here to view the sections of the SCF streets included with this project.
o   Includes specific sections of streets, curbs and stormwater drainage improvements
o   Speed humps on 196th E Ave will be removed and will not be replaced.  Required to initiate new request to get new ones.
o   Section Seam Sealing – The project includes cleaning out and sealing the seams for ALL street sections and curbs.
 
Approach
o   Plan is to begin with 39th St, starting from the East end and work their way to the West end.
o   Work will be done on one side of the street at a time to always have one lane available for thru traffic.
o   Homeowners will be required to park up/down the street if work is directly in front of their driveways.
o   Work will be done from inside the addition and work their way out to the 3 entrances.
o   Cherokee Pride should provide notice to homes impacted by construction activity 24-48 hours in advance. 
 
Potential impacts
o   Temporary traffic delays and lane closures.
o   Restricted Parking on the street in designated areas with BA actively enforcing with tickets 
o   Construction equipment may be stored on the street after hours & weekends
o   Trash service - BA Service will support trash cans placed outside of construction areas to be serviced.  Contact your independent trash company to determine specific steps required.
o   Post office delivery - temp mailboxes may be used when construction limits access to mailboxes
o   BA School bus department is aware and will adjust routes accordingly to help navigate around areas